- Time
- Within 30 days at the latest; if no decision is made within this period, the permit is deemed granted (Law No. 3194, Art. 30)
- Fee
- The building inspection and document fees in the municipal council’s fee schedule are payable; for the items see the fee schedules.
Who can apply
The owner of the building or their legally authorised representative.
Required documents
- Written request (dilekçe)
- Reports by the technical supervisors (fenni mesul) or the building inspection firm stating that the building has been completed in accordance with the permit and its annexes
How it works
- When the building is fully or partly completed, apply to the Zoning and Urban Planning Directorate with a written request.
- The building is inspected on site; the permit is granted if it is found to comply with the building permit and its annexes and there is no technical objection to its use.
Good to know
- The applicant is not asked for street numbering and sewer connection documents; the Municipality obtains these itself from the relevant department and authority — Regulation on Zoning in Planned Areas (Planlı Alanlar İmar Yönetmeliği), Art. 65.
- Buildings without an occupancy permit are not provided with electricity, water and sewerage services (Art. 31).
Legal basis
- 3194 sayılı İmar Kanunu md. 30, 31
- Planlı Alanlar İmar Yönetmeliği md. 65
- Ula Belediye Meclisinin 16.10.2025 tarihli ve 60 sayılı kararı (2026 Ücret Tarifesi)